REDESAIN SISTEM PERPIPAAN COLUMN CRUDE OIL STRIPPER NAF625503 KE AIR FIN COOLER HFF625506 PADA PROJECT BANYU URIP

REDESIGN OF PIPING SYSTEM ON COLUMN CRUDE OIL STRIPPER NAF625503 TO AIR FIN COOLER HFF625506 AT BANYU URIP PROJECT

Akhmad Hata Efendi (6810040030)


Abstrak

Project Banyu Urip merupakan industri pengolahan minyak bumi yang dibangun sejak tahun 2011 sampai 2014 oleh PT TRIPATRA. Minyak bumi diolah melalui column crude oil stripper kemudian disalurkan melalui sistem perpipaan ke air fin cooler. Desain existing memiliki panjang jalur pipa NPS 24 sebesar 67.850 mm dan pipa NPS 8 sebesar 9.511 mm serta space yang dapat dimanfaatkan dengan baik untuk sistem perpipaan. Jalur pipa yang panjang membutuhkan biaya kebutuhan pipa sebesar Rp.3.497.760.000,00. Desain alternatif dibuat dengan tujuan mengurangi biaya untuk kebutuhan pipa dan memanfaatkan space yang tersedia. Analisa fleksibilitas terhadap sistem perpipaan harus dilakukan agar desain alternatif dinyatakan aman. Dari hasil rancangan, Analisa fleksibilitas sistem perpipaan pada desain alternatif dan desain existing memiliki kesamaan nilai fleksibilitas dibawah dari batasan yang ditentukan tetapi pada desain alternatif estimasi bill of material lebih murah dibandingkan desain existing. Bill of material pada desain alternatif lebih murah dikarenakan jalur pipa mengalami perubahan diameter dari 8 in menjadi 6 in dan perubahan jalur pipa. PT. TRIPATRA dapat mengurangi biaya pembelian material sebesar Rp. 20.160.000,00.


Abstract

Project Banyu Urip is a petroleum processing industry that was built from 2011 to 2014 by PT Tripatra. Petroleum crude oil is processed the stripper column is routed a piping system to air fin cooler. Existing designs have a length of pipe routing NPS 24 of 67.850 mm and pipes NPS 8 of 9.511 mm and spaces that can be put to good used for the piping system. Long routing of pipeline needs cost for Rp.3.497.760.000,00. Alternative designs created with the objective of reducing costs for piping system needs and utilize available space. Flexibility analysis of the piping system must be done so that the alternative design is declared safe. The results of the design, analysis flexibility alternative piping systems on the same design with the existing design, but the design of alternative estimation cheaper bill of materials. Bill of materials at a cheaper alternative pipelines due to change in diameter from 8 in to 6 in and changes in the pipe. PT. Tripatra can reduce the material cost of the purchase of Rp. 20.160.000,00.


Detil Peneliti

Dosen Pembimbing 1 :Adi Wirawan Husodo
Dosen Pembimbing 2 : Wahyudi

Program Studi : D4 - TEKNIK PERPIPAAN
Angkatan : 2010