PERFORMA TURBIN GAS SETELAH PERGANTIAN COMBUSTION CHAMBER PLTGU BLOK 1.2 PT. PJB UNIT PEMBANGKITAN GRESIK

THE PERFORMANCE OF GAS TURBINE AFTER CHANGE COMBUSTION CHAMBER GAS AND STEAM POWER PLANT BLOCK 1.2 AT PT.PJB GENERATION BUSINESS UNIT GRESIK

Hardika Putra (6313030050)


Abstrak

Permasalahan yang terjadi pada turbin gas PLTGU blok 1.2 adalah penurunan performa. Salah satu yang dilakukan oleh PT.PJB UP Gresik untuk mengatasi hal tersebut adalah Combustion Inspection (CI). Secara berkala setiap 8000 jam sekali dilakukan pergantian combustion chamber dan membersihkan kotoran yang terdapat pada turbin gas untuk menjaga performa turbin gas. Berdasarkan permasalahan yang terjadi maka akan dibandingkan performa turbin gas PLTGU blok 1.2 sebelum dan sesudah pergantian Combustion Chamber. Tempat pelaksanaan studi lapangan dan pengambilan data adalah PT.PJB Unit Pembangkit Gresik dilakukan selama On The Job Training. Perhitungan performa yang dilakukan pada tutbin gas PLTGU blok 1.2 sebelum pergantian combustion chamber efisiensi kompresor sebesar 86,37%, efisiensi turbin sebesar 77,04%, efisiensi thermal sebesar 29,97%, dan BWR (Back Work Ratio) sebesar 63,82%. Dan sesudah pergantian efisiensi kompresor sebesar 87,07%, efisiensi turbin sebesar 77,74%, efisiensi thermal sebesar 30,92%, dan BWR (Back Work Ratio) sebesar 62,74%. Berdasarkan hasil perhitungan performa turbin gas PLTGU blok 1.2 setelah pergantian combustion chamber menjadi lebih baik dengan kenaikan efisiensi sekitar 0,7% - 0,95% an penurunan BWR (Back Work Ratio) sebesar 1,08%. Kata kunci : Turbin Gas, Pergantian, Combustion Chamber, Performa.


Abstract

The problems that occurred in the gas turbine power plant block 1.2 is decreased performance. One conducted by PT.PJB UP Gresik to overcome this is Combustion Inspection (CI). Periodically every 8000 hours once made change combustion chamber and clean the dirt contained in a gas turbine to maintain the performance of gas turbines. Based on the problems that occur will compare the performance of the gas turbine power plant block 1.2 before and after change of Combustion Chamber. Place of execution of field studies and data collection is PT.PJB Gresik Power Unit carried out during the On The Job Training. Based on performance calculations performed on a gas turbine power plant block 1.2 before the turn of the combustion chamber, compressor efficiency by 86,37%, amounting to 77,04% turbine efficiency, thermal efficiency of 29,97%, and BWR (Back Work Ratio) of 63,82% and after the turn, amounted to 87,07% efficiency compressor, turbine efficiency by 77,74%, amounting to 30,92% thermal efficiency, and BWR (Back Work Ratio) of 62,74%. Based on the results of the calculation of the performance of the gas turbines in power plant block 1.2 after the turn of the combustion chamber becomes better with the increase in efficiency of about 0.7% - 0,95% and a decrease in the BWR (Back Work Ratio) of 1,08%. Keywords : Gas Turbine, Change, Combustion Chamber, Performance.


Detil Peneliti

Dosen Pembimbing 1 :Eko Julianto
Dosen Pembimbing 2 :

Program Studi : D3 - TEKNIK PERMESINAN KAPAL
Angkatan : 2013


Untuk mendapatkan versi full dari dokumen penelitian ini, Anda dapat melihat koleksi Buku Tugas Akhir di Perpustakaan Politeknik Perkapalan Negeri Surabaya pada jam kerja. Atau Anda dapat menghubungi penulis secara personal.